Residential subdivision, Willawong — acquisition to settlement
A subdivision we secured on an option and held through a three-year court appeal — acquisition, approval, finance, construction and sales, one team across six years.
Read the project →Engineering, approvals and delivery — from the client side
Most projects pass through four or five firms. A planner who leaves once the approval lands. An engineer who designs the services and moves on. A project manager who arrives after the design is fixed and inherits whatever was decided without them. Every handover is a place for something to be lost — and the client is the only party present for all of it.
Zedz carries the whole span. We have taken sites from acquisition through approval, funding, design, construction and sale — and we take individual stages too, when that is what a project needs.
Why Zedz
Our principal is a Chartered Professional Engineer (CPEng) and Registered Professional Engineer of Queensland (RPEQ) with a PhD and more than 17 years of experience — technical authority and delivery discipline in the same person.
What we do
Most projects pass through four or five firms, and every handover is a place for something to be lost. We hold the whole span — or any single stage of it.
Site identification, acquisition and feasibility.
Approvals pathway management — and appeals when the answer is no.
Funding applications, development finance and lender requirements.
Hydraulic engineering from concept to detailed design, and coordination of the whole design team.
Procurement and construction-stage support as the client's representative.
Certification, commissioning, handover and defects.
Our work
Every one of these ran into something. These are the obstacles we met and what we did about them.
A subdivision we secured on an option and held through a three-year court appeal — acquisition, approval, finance, construction and sales, one team across six years.
Read the project →A community organisation had spent ten years looking for land. We found the site — then won a community use approval on ground carrying four separate constraints.
Read the project →A childcare centre and associated civil works on an operating school campus — funded, designed and delivered on schedule and on budget.
Read the project →Whether you are looking at a site you have not bought yet, or need experienced support part-way through delivery, we bring clarity to the complex.