- Client
- Private developer, Willawong
- Location
- Willawong, QLD
- Service
- Development management, approvals, finance and construction management
- Status
- Under construction and presales
- Years
- 2020–
Residential subdivision, Willawong — acquisition to settlement
A subdivision we secured on an option and held through a three-year court appeal — acquisition, approval, finance, construction and sales, one team across six years.
The challenge
The site carried heavy council and State ecological constraints, and council refused the application. The appeal ran three years. An option has an expiry date, and three years of argument can outlast the instrument holding the land — if it lapses, the site goes back to the market and the approval work goes with it. Ecology and land development are usually argued as opposites, and on that framing this site loses.
What we did
We secured the site on an option before the approvals were sought, giving the client control of the land without committing the capital, and we held that position for six years. As the appeal ran, we renegotiated and extended the option twice, so the site was never at risk while the argument continued. In the Planning and Environment Court we set the position, instructed and directed the planning and legal specialists, and held the case together across three years, on the argument that ecological protection and land development were not in opposition but could be balanced in the development footprint. We won. We obtained operational works approval in 2025, the land settled on the strength of it, and we carried the project on through presales, finance and construction management.
Outcome
Appeal upheld in the Planning and Environment Court in 2024. Operational works approved and the land settled in 2025, finance obtained in 2026, with construction underway. The site was never lost — secured on option in 2020, held through a three-year appeal, delivered to construction six years later.
Project phases
- Option secured over the site2020Complete
- Development application2021Lodged
- Appeal — Planning and Environment Court2022–2024Won
Three years arguing for a balanced development outcome between ecology and land development. Option renegotiated and extended twice during the appeal.
- Operational works approval and settlement2025Complete
- Presales coordination2025–In progress
- Finance2026Obtained
- Construction management2026–Underway